Daniels Sanitation District-Sewer Line Rehabilitation June 8th - June 12th 2026

QP Services has been contracted by Daniels Sanitation District to install CIPP (Cured-In-Place-Pipe) liners inside select sewer main sections/runs starting on Monday June 8, 2026 through Friday, June 12th, 2026. This is a trenchless rehabilitation method that will repair our aging sewer main infrastructure without the inconvenience of local street excavation. The special liner is inserted into the main, where it is expanded and cured into place, creating a new pipe.

There are four sections/runs of sewer main that will be rehabilitated during this time and the specific addresses that will be impacted are listed below:

Zinna St.

777 Zinnia St.

776 Zinnia St.

767 Zinnia St.

766 Zinnia St.

757 Zinnia St.

756 Zinnia St.

747 Zinnia St.

746 Zinnia St.

736 Zinnia St.

717 Zinnia St.

716 Zinnia St.

W. 6th Dr.

12617 W. 6th Pl.

12611 W. 6th Dr.

12631 W. 6th Dr.

12632 W. 6th Dr.

12651 W. 6th Dr.

12652 W. 6th Dr.

12671 W. 6th Dr.

12672 W. 6th Dr.

W. 8th Ave. & Urban St.

795 Urban St.

794 Urban St.

785 Urban St.

784 Urban St.

 

Parfet St.

810 Quail St.

928 Quail St.

855 Parfet St.

The rehabilitation process per section/run will take approximately 4-6 hours. During this time, the sewer main will be temporarily out of service. Residents will need to limit water usage as much as possible to prevent their sewer service line from backing up. If you are a customer in the rehabilitation zone and experience a sewer line back-up, call our office immediately at 303-233-2182.